FERRY TERMINAL IN DURRËS PORT – IMPLEMENTATION OF ELECTRICAL SYSTEMS

Year: 2012

Client: Durrës Port Authority

Elteknik has carried out the implementation of electrical systems for the new Ferry Terminal in the Port of Durres in 2012. The new ferry terminal was built to provide a quality service to travelers using this port. The project includes all public service areas of the terminal, staff offices, auxiliary areas and technical areas.

The services provided by Elteknik for this project include

Implementation of:

  • Electrical Substation, Transformers and MV Switchgears
  • Generators and UPS
  • Main Supply Switchboards and Distribution Switchboards
  • Cable trays and infrastructure for electrical installations
  • Power installations
  • Lighting System
  • Data Network
  • Lightning Protection System
  • Emergency Lighting System
  • Fire Detection System
  • Audio and Voice Evacuation System
  • Access Control System
  • Video Monitoring System
  • BMS system